Grand Opening
From Kwartzlab
(Difference between revisions)
(→Time Line) |
|||
| (31 intermediate revisions by one user not shown) | |||
| Line 1: | Line 1: | ||
[[Category:Hackerspace]] | [[Category:Hackerspace]] | ||
| + | |||
| + | = Time Line = | ||
| + | |||
| + | == Not Scheduled Yet == | ||
| + | * paint door & towel rack with glossy black enamel (Ben) | ||
| + | * install lattice in work room (Mark & Caelyn) | ||
| + | * purchase liquor | ||
| + | * arrange catering (Natalie, Cedric) | ||
| + | |||
| + | |||
| + | == Thursday Sept 24 == | ||
| + | * Sand & prime the Lounge (Michael) | ||
| + | * take fridge to curb | ||
| + | * take any other garbage or recycling to curb | ||
| + | * posters need to be put up all around town | ||
| + | |||
| + | == Friday Sept 25 == | ||
| + | * Paint the Lounge -- 2 coats (Michael) | ||
| + | * posters need to be put up all around town | ||
| + | |||
| + | == Saturday Sept 26 == | ||
| + | * Two Hands Project visits | ||
| + | * tiling the kitchen (Gus, Cheryl?) | ||
| + | * replace glass window panes (Gus) | ||
| + | * paint window frames (Steph) | ||
| + | * *if painting is done* arrange furniture/shelving in lounge | ||
| + | |||
| + | == Sunday Sept 27 == | ||
| + | * complete anything from Saturday which is not yet finished | ||
| + | * drop off projects | ||
| + | |||
| + | == Monday Sept 28 == | ||
| + | * Complete anything from Sunday which is not finished | ||
| + | * Deadline for ordering party trays from Vincenzo's or Zehrs | ||
| + | |||
| + | == Tuesday Sept 29 == | ||
| + | * Complete anything from Monday which is not finished | ||
| + | |||
| + | == Wednesday Sept 30 == | ||
| + | * final clean-up and prep (Steph, Ben, Bevan, Darin, Michael) | ||
| + | |||
| + | == Thursday Oct 1 == | ||
| + | * pick up small bills and change for cash box | ||
| + | * set up bar | ||
| + | * set up food table | ||
| + | |||
| + | == During the Event == | ||
| + | * Bartenders: | ||
= Advertising = | = Advertising = | ||
| Line 6: | Line 54: | ||
= Space Prep = | = Space Prep = | ||
== Front Door & Signage == | == Front Door & Signage == | ||
| − | * front door needs to be painted with glossy black enamel paint | + | * front door needs to be painted with glossy black enamel paint (Ben has paint and has volunteered to do the door) |
== Lounge == | == Lounge == | ||
| Line 12: | Line 60: | ||
* remove anything we're not keeping | * remove anything we're not keeping | ||
* wash the floors. again. | * wash the floors. again. | ||
| − | * project displays | + | * project displays |
* kwartzlab info displays? | * kwartzlab info displays? | ||
* garbage bin | * garbage bin | ||
| Line 31: | Line 79: | ||
= Food & Drink = | = Food & Drink = | ||
| − | * need a cash box with small bills/change | + | * need a cash box (Eric/Alex should have) with small bills/change |
== Catering == | == Catering == | ||
| − | * order food | + | * order food, soft drinks |
| − | * plates, cutlery, napkins | + | * plates, cutlery, napkins, cups |
== Booze == | == Booze == | ||
* liquor license is in hand | * liquor license is in hand | ||
* need to order & pick up liquor -- how much? | * need to order & pick up liquor -- how much? | ||
| − | |||
=== Bartending === | === Bartending === | ||
= Presentations = | = Presentations = | ||
| + | |||
| + | * President's closing remarks/toast | ||
Latest revision as of 16:45, 25 September 2009
Contents |
Time Line
Not Scheduled Yet
- paint door & towel rack with glossy black enamel (Ben)
- install lattice in work room (Mark & Caelyn)
- purchase liquor
- arrange catering (Natalie, Cedric)
Thursday Sept 24
- Sand & prime the Lounge (Michael)
- take fridge to curb
- take any other garbage or recycling to curb
- posters need to be put up all around town
Friday Sept 25
- Paint the Lounge -- 2 coats (Michael)
- posters need to be put up all around town
Saturday Sept 26
- Two Hands Project visits
- tiling the kitchen (Gus, Cheryl?)
- replace glass window panes (Gus)
- paint window frames (Steph)
- *if painting is done* arrange furniture/shelving in lounge
Sunday Sept 27
- complete anything from Saturday which is not yet finished
- drop off projects
Monday Sept 28
- Complete anything from Sunday which is not finished
- Deadline for ordering party trays from Vincenzo's or Zehrs
Tuesday Sept 29
- Complete anything from Monday which is not finished
Wednesday Sept 30
- final clean-up and prep (Steph, Ben, Bevan, Darin, Michael)
Thursday Oct 1
- pick up small bills and change for cash box
- set up bar
- set up food table
During the Event
- Bartenders:
Advertising
- Posters need to be posted around town
Space Prep
Front Door & Signage
- front door needs to be painted with glossy black enamel paint (Ben has paint and has volunteered to do the door)
Lounge
- shelving needs to be re-arranged to open the space back up
- remove anything we're not keeping
- wash the floors. again.
- project displays
- kwartzlab info displays?
- garbage bin
Work Room
- wash the floors. again.
- tables for food/beverage service
- garbage bin
Kitchen
- floor needs to be tiled
- garbage bin
Bathroom
- bathroom needs to be cleaned right before the party
- towel rack hung, and fresh towel(s) in place
- check hand soap & toilet paper
Food & Drink
- need a cash box (Eric/Alex should have) with small bills/change
Catering
- order food, soft drinks
- plates, cutlery, napkins, cups
Booze
- liquor license is in hand
- need to order & pick up liquor -- how much?
Bartending
Presentations
- President's closing remarks/toast